Future Work
| Date | Richard | Wei Hao | Sowmya | Mingchuan |
|---|---|---|---|---|
| End Dec | - Data transfer via CAN | - Procure suitable convertor - V0 of High Voltage PCB - GM Tube calibration with Mingchuan | - Design V0 of Experiment PCB | - Update shielding design required (top, centre, bottom) and send for prototyping - GM Tube calibration with Wei Hao |
| Mid Jan | - HEX to CSV program | - Testing V0 and refine design for V1 - Provide GM Tube counts to Richard to store | - Testing V0 and refine design for V1 | - Check fitting and mounting - SolidWorks Analysis for vibration, shock and thermal test |
| End Jan | - C&C via CAN | - Testing V1 and refine design for V2 | - Finalise shielding and mounting designs, send for manufacturing | |
| Milestone 1: Finalise design | ||||
| Mid Feb | - Port to RTOS | - Integrating PCB design with other electrical member | - SolidWorks Analysis for vibration, shock and thermal test - Rideshare integration design | |
| End Feb | - Integrate all experiment code - Adopt rideshare stack | - Assembly of mechanical parts with electric and software | ||
| Milestone 2: Finalise integration for systems testing | ||||
| Mid Mar | - Code optimisation | - Testing the Integrated PCB V2 and final characterization - Mechanical testings with ST Engineering: Vibration, Impact, Thermal - Refine mechanical designs if needed | ||
| End Mar | - Complete stress testing | - Mechanical testings with ST: Vibration, Impact, Thermal (if required) - Rideshare integration | ||
| Milestone 3: Complete systems testing | ||||
| Mid Apr | - Final Full Payload Prelaunch Checks and Admin work | |||
| End Apr | - FYP Presentation and Waiting for Launch | |||